FY 2021 Educational Facilities Master Plan

14 Chipman Elementary

Facility Needs

14.06.346 Systemic Renovation - HVAC In 2021, the existing HVAC equipment will have been in service for 35 years and will have out lived its useful lifespan. Project Description The project includes the systemic replacement of approximately 28 above ceiling heat pump units and various AHU's. Replacement of the units will allow for continued operation of the school's HVAC system utilizing a more energy efficient model.

Project Notes The cooling tower had to be replaced in the spring of 2014, this bought some time.

CNTY: -Approved a portion of the project in FY2015 CIP

STATE: -Deferred in FY 15 due to fiscal constraints.

Gym and Cafe AHU's replaced in 2017 due to failure.

14.06.396 Systemic Renovation - Lighting Systems Lighting systems and ceilings have passed their useful life. Upgrades are needed in order to provide adequate lighting levels and additional operational efficiencies. Project Description Upgrade lighting fixtures and associated ceilings that have exceeded their life cycle in Areas A, B & C. Project includes electrical service upgrades and branch wiring as required to accommodate new lighting. Project Notes Coordinate with the HVAC project.

Wicomico County Public Schools Educational Facilities Master Plan FY 2020

118

Made with FlippingBook Ebook Creator