43.032.282 Site - Fields and Grounds The current football practice field lacks lighting. Project Description
Design and install lighting at the existing football practice field.
43.032.359 Site - Fields and Grounds Parkside has requested an athletic stadium be built. Community interest has been expressed and some funds pledged toward the construction of such a facility. Project Description Collected funds would be utilized to study the feasibility and cost of a stadium complex as requested by the school. 43.06.515 Special Initiatives - Electrical Wicomico Emergency Management has requested a generator be installed at the school to allow Parkside to operate as a tier 3 emergency refuge. Project Description Install required generator. 43.05.138 Special Initiatives - Science (Look of the Future) State initiative to upgrade and modernize science classrooms in all high schools for the next century.
Project Description These funds would allow for the design and renovation of the existing science facilities.
43.13.532 Systemic Renovation - Roofs The roof has outlived its useful life. Project Description
Replace existing roof - approximately 128,585 sf.