3 18.13.528 Westside Intermediate: Systemic Renovation - Roofs
As part of the Roof Refurbishment Program this school is due for a roof replacement.
Identified area includes the entire low-slope roof at 55,691 sq.ft., average age of roof area was 20 years in 2019. Project Description
Estimate/Funding Initial Total Estimate 10/01/2014 $1,350,000
Revised Total Estimate $2,035,000 06/06/2019
Prev. Approved Funding
County
State
$281,000
$0
Cost Share Split of Total Estimate
Remaining Funding
State
County
County
State
$0
$2,035,000
$1,754,000
$0
4 6.13.538 Glen Ave Elementary: Systemic Renovation - HVAC
The existing HVAC systems have reached the end of their useful life.
Provide new energy efficient HVAC systems based on latest codes and available technologies. Project Description
Estimate/Funding Initial Total Estimate 05/01/2018 $4,297,000
Revised Total Estimate $3,863,000 08/28/2020
Prev. Approved Funding
County
State
$0
$0
Cost Share Split of Total Estimate
Remaining Funding
State
County
County
State
$0
$3,863,000
$3,863,000
$0