FY 2022 Capital Improvement Plan & Budget
06 Glen Ave Elementary
FY2022
6.11.570 Site - Paving / Parking Lots The parking lot is undersized and there are circulation issues with parent and bus drop off that rise safety concerns.
Project Description
Design and construct revised parking area. Funds are to secure design services only.
Estimated Cost Initial
Revised
Cost Share Split
County
State
$75,000
05/09/2019
$0
$75,000
$0
Funding
Prev. Approved
2022
2023
2024
2025
2026
2027
Out Years
Total $75,000 $0 $75,000
County State
$0 $0
$0
$75,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$75,000
$0
$0
$0
$0
$0
Fiscal Year County Requested State Requested County Deferred State Deferred County Approved State Approved 2021 $75,000 $0 $75,000 $0 $0 $0 Funding History
50
WCBOE: Planning + Construction
FY2022 CIP (FINAL rev. 9/3/2020)
Made with FlippingBook - Online Brochure Maker