FY 2022 Capital Improvement Plan & Budget

06 Glen Ave Elementary

FY2022

6.13.537 Systemic Renovation - Windows / Doors/ Hdwr The existing exterior windows and doors have reached the end of their useful life.

Project Description

Project includes new exterior insulated, energy efficient windows and doors.

Estimated Cost Initial

Revised

Cost Share Split

County

State

$850,000

05/01/2018

$0

$850,000

$0

Funding

Prev. Approved

2022

2023

2024

2025

2026

2027

Out Years

Total $850,000 $0 $850,000

County State

$0 $0

$850,000

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

Total

$0

$850,000

$0

$0

$0

$0

$0

$0

55

WCBOE: Planning + Construction

FY2022 CIP (FINAL rev. 9/3/2020)

Made with FlippingBook - Online Brochure Maker