8.13.553 Systemic Renovation - Windows / Doors/ Hdwr The existing interior and exterior windows and doors have reached the end of their useful life.
Project Description
Project includes new insulated, energy efficient windows and storefront and associated masonry repairs required for installation. Project also includes new interior doors and hardware.
Estimated Cost Initial
Revised
Cost Share Split
County
State
$685,000
08/06/2018
$0
$685,000
$0
Funding
Prev. Approved
2022
2023
2024
2025
2026
2027
Out Years
Total $685,000 $0 $685,000