10 Pinehurst Elementary

FY2022

10.06.399 Systemic Renovation - Lighting Systems Lighting systems and ceilings have passed their useful life. Upgrades are needed in order to provide adequate lighting levels and additional operational efficiencies.

Project Description

Upgrade lighting fixtures in areas A through F and associated ceilings that have exceeded their useful lives. Project includes electrical service upgrades and branch wiring as required to accommodate new lighting.

Estimated Cost Initial

Revised

Cost Share Split

County

State

$1,228,000

09/01/2013

$1,345,000

07/09/2018

$1,345,000

$0

Funding

Prev. Approved

2022

2023

2024

2025

2026

2027

Out Years

Total $1,345,000 $0 $1,345,000

County State

$0 $0

$1,345,000

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

$0

Total

$0

$1,345,000

$0

$0

$0

$0

$0

$0

65