FY 2022 Capital Improvement Plan & Budget
10 Pinehurst Elementary
FY2022
10.13.569 Systemic Renovation - Plumbing The fixtures, finishes, accessories and partitions in the toilet rooms have either already reached or will be reaching the end of their life cycle, which necessitates replacement.
Project Description
Renovate existing toilet rooms. Analyze toilet rooms for accessibility.
Estimated Cost Initial
Revised
Cost Share Split
County
State
$1,080,000
03/29/2019
$0
$1,080,000
$0
Funding
Prev. Approved
2022
2023
2024
2025
2026
2027
Out Years
Total $1,080,000 $0 $1,080,000
County State
$0 $0
$0
$0
$0
$1,080,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$0
$0
$1,080,000
$0
$0
$0
67
WCBOE: Planning + Construction
FY2022 CIP (FINAL rev. 9/3/2020)
Made with FlippingBook - Online Brochure Maker