FY 2022 Capital Improvement Plan & Budget
14 Chipman Elementary
FY2022
14.06.466 Systemic Renovation - Security and/or Fire Alarm The existing fire alarm system has reached the end of its useful life in Areas A through C.
Project Description
Upgrade or replace the existing fire alarm system in Areas A through C.
Estimated Cost Initial
Revised
Cost Share Split
County
State
$215,000
10/01/2013
$235,000
07/09/2018
$235,000
$0
Funding
Prev. Approved
2022
2023
2024
2025
2026
2027
Out Years
Total $235,000 $0 $235,000
County State
$0 $0
$0
$235,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$235,000
$0
$0
$0
$0
$0
Fiscal Year County Requested State Requested County Deferred State Deferred County Approved State Approved 2019 $207,000 $0 $207,000 $0 $0 $0 Funding History