FY 2022 Capital Improvement Plan & Budget
17 Westside Primary
FY2022
17.04.380 Addition - Studies / Planning Currently Westside Primary has a cafetorium which serves as its cafeteria, gymnasium and auditorium. As student population continues to increase it's become more of a challenge to schedule the multiple needs that this shared assembly space requires. The school is in need of a separate Gymnasium to serve students physical education needs and help assist with the over-scheduling of the existing cafetorium.
Project Description
Conduct a feasibility study to investigate the options for a separate Gymnasium with the necessary support space applicable to this programmatic need.
Estimated Cost Initial
Revised
Cost Share Split
County
State
$35,000
10/01/2015
$4,146,000
08/15/2017
$1,719,000
$2,427,000
Funding
Prev. Approved
2022
2023
2024
2025
2026
2027
Out Years
Total $1,719,000 $2,427,000 $4,146,000
County State
$0 $0
$0
$0
$55,000 $1,664,000
$0
$0
$0
$0
$0
$0
PLANNING $2,427,000
$0
$0
Total
$0
$0
$0
$55,000 $1,664,000 $2,427,000
$0
$0
77
WCBOE: Planning + Construction
FY2022 CIP (FINAL rev. 9/3/2020)