FY 2022 Capital Improvement Plan & Budget
43 Parkside High
FY2022
43.13.532 Systemic Renovation - Roofs The roof has outlived its useful life.
Project Description
Replace existing roof - approximately 128,585 sf.
Estimated Cost Initial
Revised
Cost Share Split
County
State
$4,855,000
07/06/2018
$6,296,000
06/16/2020
$1,031,000
$5,265,000
Funding
Prev. Approved
2022
2023
2024
2025
2026
2027
Out Years
Total $1,031,000 $5,265,000 $6,296,000
County State
$0 $0
$0
$0
$1,031,000
$0
$0
$0
$0
$0
$0
$0
$5,265,000
$0
$0
$0
Total
$0
$0
$0
$1,031,000 $5,265,000
$0
$0
$0