46 Wicomico High School
FY2022
46.13.547 Systemic Renovation - Plumbing The auditorium toilet room fixtures, finishes, accessories and partitions have reached the end of their life cycle, which necessitates replacement.
Project Description
Renovate existing auditorium toilet rooms. Analyze toilet rooms for accessibility.
Estimated Cost Initial
Revised
Cost Share Split
County
State
$514,000
05/01/2018
$550,000
06/10/2019
$550,000
$0
Funding
Prev. Approved
2022
2023
2024
2025
2026
2027
Out Years
Total $550,000 $0 $550,000
County State
$0 $0
$0
$550,000
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
$0
Total
$0
$0
$550,000