FY2021 C.I.P. Deferred Projects
The following report lists projects and funding requests that were included as part of last year's Capital Budget Request but were not approved for funding. These deferred projects may be included in the current year's request or in a future year's request.
Project
County
State
Project #
$865,559 *
1.14.507
Beaver Run: Replacement School - Construction
$0
2.11.560
Delmar Elementary: Site - Paving / Parking Lots
$80,000
$0
6.13.574
Glen Ave Elementary: Systemic Renovation - Mechanical
$56,000
$0
6.11.570
Glen Ave Elementary: Site - Paving / Parking Lots
$75,000
$0
6.7.566
Glen Ave Elementary: Renovation - Studies / Planning
$75,000
$0
8.04.379
Northwestern Elementary: Addition - Studies / Planning
$1,664,000
$0
10.06.416 Pinehurst Elementary: Systemic Renovation - Elevators / Conveying $450,000
$0
11.13.575 Pittsville Elem / Middle: Systemic Renovation - Security and/or Fire Alarm
$351,000
$0
18.13.528 Westside Intermediate: Systemic Renovation - Roofs
$0
$1,754,000
* Indicates that a funding request was only partially funded